44849-soroti-thumbnail.jpg
 

Soroti. Ground mounted Solar Power Plant.  

The First Grid-connected Solar Power Plant in Uganda Starts Operations!

The 10 MW plant (32,680 solar modules on 13 hectares) became the first grid-connected solar power plant in Uganda, but also East Africa’s largest photovoltaics plant at date of commissioning. 

Read more >>

 

63306-kikari-pic.jpg
 
 

Kakira. Bio mass plant.

20 MW biomass (bagasse from sugar production) plant in Jinja District, Eastern Uganda. The plant is expected to deliver up to 147 GWh/year to the grid. Total investment is USD 57M with about USD 7.1M in GET FIT commitments.

Kakira Sugar Ltd. became the first recipient of a GET FiT premium payment in September 2015.

Read more >>

 

 

82912-siti-thumbnail.jpg
 
 

Siti I. Run-of-river Hydro Power Plant

Planned installed capacity of 6.1 MW and estimated 29 GWh annual production located in Bukwo District, Eastern Uganda.

Investment of USD 14.8M with USD 3.6M in GET FiT commitments. Construction was commenced in March 2015, expected COD in March 2017

Read more >>

 

 

 

 

42436-muvumbe-thumbnail.jpg
 
 

Muvumbe. Run-of-river Hydro Power Plant

Planned installed capacity of 6.5 MW and 31 GWh annual production. The project located is in Kabale district.

Investment of USD 14.1M with USD 4.5M in GFPPM commitments. The project commenced construction works in September 2015 and has been progressing well.

Read more >>

 

89402-rwimi-thumbnail.jpg
 
 

Rwimi. Run-of-river Hydro Power Plant

Planned installed capacity of 5.5 MW and estimated 27 GWh annual production, located in Kasese district. Investment of USD 20.8M with USD 3.9M in GET FiT commitments.

Construction works initiated in 2015, and expected commercial operation date is Q3 2017.

Read more >>

 

 

 

 

80865-nkusi-thumbnail.jpg
 
 

Nkusi. Run-of-river Hydro Power Plant

Nkusi. Run-of-river HPP with a planned installed capacity of 9.6 MW and 46 GWh in annual production.

The project is located in the Kibaale and Hoima districts. Investment of USD 23M with USD 6.5M in GFPPM commitments.

Read more >>

 

24293-nyamwamba.thumbnail.jpg
 
 

Nyamwamba. Run-of-river Hydro Power Plant

Planned installed capacity of 9.2 MW and estimated 39 GWh annual production, located in Kasese district. Investment of USD 26.8M with USD 5.8M in GET FiT commitments.

The project started construction in Q4 2015. Expected commercial operation date is Q1 2018. 

Read more >>

 

33759-kyambura-thumbnail.jpg  

Lubilia. Run-of-river Hydro Power Plant

Planned installed capacity: 5.4 MW and expected 25 GWh annual production, located in Kasese district. Investment of USD 18.7M with USD 3.2M in GET FiT commitments.

The developer commenced construction in 2016 after clearing the final environmental and social CPs. Expected commercial operation date is Q4 2017. 

Read more >>

 

48908-waki-thumbnail.jpg
 
 

Waki. Run-of-river Hydro Power Plant

Planned installed capacity of 4.8 MW and estimated 25 GWh annual production located in Hoima and Bulisa District, Western Uganda. Investment of USD 18.1M with USD 3.6M in GET FiT commitments.

Financing is now secured. Commissioning expected late 2017.

Read more >>

 

 

 

82912-siti-thumbnail.jpg
 
 

Siti II. Run-of-river Hydro Power Plant

Planned installed capacity of 16 MW and estimated 72 GWh annual production located in Bukwo District, Eastern Uganda. Investment of USD 33M with USD 10.2M in GET FiT commitments.

Expected commercial operation date in Q3 2018.

Read more >>

 

 

 

 

81212-sindila-thumbnail.jpg
 
 

Sindila. Run-of-river Hydro Power Plant

Planned installed capacity of 5 MW and 27 GWh expected annual production located in Bundibugyo district. Investment of USD 17M with USD 3.3M in GET FiT commitments.

Sindila was the last project to be selected from the second RFP round, after a re-appraisal of the project was conducted in October 2014.

Read more >>

 

 

 

 

 

33759-kyambura-thumbnail.jpg  

Kymbura. Run-of-river Hydro Power Plant

Planned installed capacity of 7.6 MW and 36.7 GWh in annual production. The project is located in the Rubirizi district. Investment of USD 24M with USD 5.4M in GFPPM commitments.

Approved for GET FiT support after RFP 3 in June 2015. DFA signed in 2016.

Read more >>

 


 
 

Tororo. Ground mounted solar PV Power Plants

Located in Tororo district, with a planned peak capacity of 10 MWp and an average annual energy production of 16.7 GWh. Investment of USD 20M with USD 8.6M in GET FiT Commitments.

The developer expects to reach COD in Q3 2017.

Read more >>

 

 

 

 


 
 

Kikigati. Run-of-river Hydro Power Plant

Planned installed capacity of 16 MW and 115 GWh annual production located in Isingiro district, Southern Uganda on the border to Tanzania. Investment of USD 51.1M with USD 12.3M in GFPPM commitments.

Construction is planned to commence within the first half of 2017.

Read more >>

 

 

 

 

   

Nyamagasani I + II. Run-of-river Hydro Power Plants

Both projects are located in the Kasese district.

Construction start for both projects is expected within Q1 2017.

Read more >>

 

   

Ndugutu. Run-of-river Hydro Power Plant

Planned installed capacity of 4.8 MW and 22 GWh in annual production. The project is located in the Bundibugyo district. Investment of USD 15M with USD 3.2M in GFPPM commitments. Approved for GET FiT support after RFP 3 in June 2015. DFA signed in 2016. 

Construction start is expected in early 2017.

Read more >>