Siti I. Run-of-river Hydro Power Plant

The Siti I SHP is a run-of-river plant with an installed capacity of 6.1 MW and estimated 29 GWh annual production, located in Bukwo District, Eastern Uganda. 

The Project secured investments of USD 14.8M, with USD 3.6M in GET FiT commitments. 

The Project has the longest waterway in the GET FiT portfolio at more than 5 km in length.

Read more >>

 

 

 

 


42436-muvumbe-thumbnail.jpg
 
 

Muvumbe. Run-of-river Hydro Power Plant

Installed capacity 6.5 MW and estimated 31 GWh annual production, located in Kabale District, South-Western Uganda. 

The Project secured investments of USD 14.1M and USD 4.5M in GET FiT commitments, under the second request for proposals for the GET FiT Premium Payment Mechanism (GFPPM) in Uganda. 

Read more >>

 

 


89402-rwimi-thumbnail.jpg
 
 

Rwimi. Run-of-river Hydro Power Plant

Installed capacity of 5.5 MW and estimated 27 GWh annual production, located in Kasese district, western Uganda. 

The Project secured investments of USD 20.8M and USD 3.9M in GET FiT commitments, under the first request for proposals for the GET FiT Premium Payment Mechanism (GFPPM) in Uganda.   

Read more >>

 

 

 

 


53684-tororo-2.png
 

Tororo. The Second Grid-connected Solar Power Plant in Uganda Starts Operations

The 10 MW plant (32,240 solar modules on 14 hectares) became the second grid-connected solar power plant in Uganda. The Tororo Solar Power Plant will produce around 16 GWh each year.
 

Read more >>

 

 

 

 


44849-soroti-thumbnail.jpg
 

Soroti. Ground mounted Solar Power Plant.  

Soroti has been injecting power to the national grid for more than a year now.

The 10 MW plant (32,680 solar modules on 13 hectares) developed by Access Uganda Solar Ltd. was, at the beginning of commercial operation, the first grid-connected Solar Power Plant in Uganda.  

Read more >>

 

63306-kikari-pic.jpg
 
 

Kakira. Bio mass plant.

A 20 MW biomass (bagasse from sugar production) plant in Jinja District, Eastern Uganda.

The plant is designed to deliver 147 GWh/year to the grid. 

Read more >>

 

 

80865-nkusi-thumbnail.jpg
 
 

Nkusi. Run-of-river Hydro Power Plant

Nkusi. Run-of-river HPP with a planned installed capacity of 9.6 MW and 46 GWh in annual production.

The project is located in the Kibaale and Hoima districts. Investment of USD 23M with USD 6.5M in GFPPM commitments.

Read more >>

 

24293-nyamwamba.thumbnail.jpg
 
 

Nyamwamba. Run-of-river Hydro Power Plant

Planned installed capacity of 9.2 MW and estimated 39 GWh annual production, located in Kasese district. Investment of USD 26.8M with USD 5.8M in GET FiT commitments.

The project started construction in Q4 2015. Expected commercial operation date is Q1 2018. 

Read more >>

 


33759-kyambura-thumbnail.jpg
 

Lubilia. Run-of-river Hydro Power Plant

Planned installed capacity: 5.4 MW and expected 25 GWh annual production, located in Kasese district. Investment of USD 18.7M with USD 3.2M in GET FiT commitments.

The developer commenced construction in 2016 after clearing the final environmental and social CPs. Expected commercial operation date is Q1 2018. 
 

Read more >>

 

48908-waki-thumbnail.jpg
 
 

Waki. Run-of-river Hydro Power Plant

Planned installed capacity of 4.8 MW and estimated 25 GWh annual production. Investment of USD 18.1M with USD 3.6M in GET FiT commitments.

The Developer addressed key issues and resumed construction works during Q4 2017 and is aiming to achieve commercial operation during Q3 2018.

Read more >>

 

 

 

82912-siti-thumbnail.jpg
 
 

Siti II. Run-of-river Hydro Power Plant

Planned installed capacity of 16 MW and estimated 72 GWh annual production located in Bukwo District, Eastern Uganda. Investment of USD 33M with USD 10.2M in GET FiT commitments.

Expected commercial operation date in Q3 2018.

Read more >>

 

 

 

 

 


33759-kyambura-thumbnail.jpg
 

Kymbura. Run-of-river Hydro Power Plant

Planned installed capacity of 7.6 MW and 36.7 GWh in annual production. The project is located in the Rubirizi district. Investment of USD 24M with USD 5.4M in GFPPM commitments.

The Developer plans for a COD in Q4 2018 but, given the aggressive construction schedule, Q1-Q2 2019 seems more likely.

Read more >>

 


81212-sindila-thumbnail.jpg
 
 

Sindila. Run-of-river Hydro Power Plant

Planned installed capacity of 5 MW and 27 GWh expected annual production.

Construction activities commenced during early 2017 and the Developer plans to achieve the COD during Q3 2018. 

However, the construction programme and terrain are challenging and a COD during Q1-Q2 2019 appears more realistic at this stage.

Read more >>

 

 

 

 


25558-ndugutu-small.png
 

Ndugutu. Run-of-river Hydro Power Plant

Run-of-river SHP with a planned installed capacity of 5.9 MW and 26.5 GWh in annual production.

Construction activities commenced during Q2 2017, with the Developer aiming for commercial operation during Q4 2018.

Read more >>

 


44259-nyamagasani-small.png
 

Nyamagasani I + II. Run-of-river Hydro Power Plants

Both projects are located in the Kasese district.

Construction started for both projects in Q1 2017.

Nyamagasani I is aiming for commercial operation
during Q4 2018.

Read more >>

 


86637-kikigati-small.png
 

Kikigati. Run-of-river Hydro Power Plant

Planned installed capacity of 16 MW and 115 GWh annual production. Investment of USD 51.1M with USD 12.3M in GFPPM commitments.

Following substantial delays, the Project mobilised to site during Q4 2017